34 化工厂常用PSSR检查表——国外

VIP免费
3.0 2024-07-25 0 0 870KB 40 页 1库币 海报
投诉举报
开车检查表(质控部分)
Description of System/Area Under Review
所审查系统/区域的描述
Date
日期
Time
时间
Item No.
序号
Recommendation(Type Action Below or ‘not applicable’)
建议(请填写下列行动项或注明“不适用”)
结果
文件部分
1.
2.
3.
4.
5.
6.
7.
8.
System Checkout Items
系统检查项目
9. Complete/document quality assurance program:
完成质量保证体系并建立了文档
a) Received equipment=purchased
收到的设备=购买的设备
b) Adherence to design drawings/specifications
采用的设计规范
c) Materials of construction
施工材料
d) Workmanship
工艺技术
. Equipment components checkout/commissioning (document)
设备部件检查/调试(文件)
10. Loop and interlock/permissive/alarm: set point adjustment and
testing (document results)
回路和联锁/许可/报警:设置点调整和测试(文档记录)
11. Instrument calibrations done and documented
仪表校订完成并记录
12. Validation protocol developed, approved and executed
制定、批准和执行的验证协议
13. Pressure testing done and documented
压力测试完成并记录
14. System cleaned and flushed
系统已完成清扫、冲洗
15. Fire protections systems inspected, acceptance-tested
documentation provided
消防系统已检查,并有测试、验收记录
Item No.
序号
Recommendation(Type Action Below or ‘not applicable’)
建议(请填写下列行动项或注明“不适用”)
结果
文件部分
16. Ventilation systems balanced
通风系统已平衡
17. Performance checkout of local exhaust systems
局部排气系统的性能检测
18. Vibration measurements/documentation
振动测量记录
19. Field radiography done and documented as required
现场放射性物质检测已完成并记录
20. Baseline data, such as thickness readings for pressure
vessels/piping
基础数据,如压力容器/管线的壁厚
21. Other baseline data
其他基础数据
22. NDT reports
无损检测报告
23. Water batching (document)
配水(记录)
Engineering Design Documentation
工程设计资料
24. Narrative of control philosophy/Sequence of operations
documentation
操作控制原理/操作顺序的说明资料
25. Instrument index
仪表索引
26. Instrument loop diagrams
仪表回路图
27. Interlock (safety & non-safety) descriptions
联锁(安全和非安全)描述
28. As-built drawings: P&IDs, electrical, piping, mechanical
竣工图:PID 图,电气图,配管图,机械图
29. Tabulation of process alarms, interlocks/permissive descriptions and
trips with settings (P&ID)
工艺报警表、联锁/许可说明表和带设定值(P&ID)的跳转表
30. Review and approval of fire protections systems design
消防系统设计的审查和许可
31. Piping specifications (P&I/mechanical drawings)
配管图(PI /机械图)
32. Pressure relief device sizing calculations
安全阀规格的选定计算
33. ASME code pressure vessels U-1 data sheets (to Maintenance)
压力容器 ASME 代码 U-1 数据表(用于维修)
34. Reference codes/standards for facility design
装置设计的参考规范/标准
35. Reference codes/standards for facility installation
设备安装的参考规范/标准
36. Design codes for specific equipment
特殊设备的设计规范
Item No.
序号
Recommendation(Type Action Below or ‘not applicable’)
建议(请填写下列行动项或注明“不适用”)
结果
文件部分
37. Welder certification
焊工资格证书
38. NDT certification
无损检测证书
39. Electrical classification drawings
电器分类图
40. Electrician certification for classified areas
特定施工区域的电工资格证书
Maintenance Items
维修项目
41. Spare parts lists developed
List equipment:
清单并
设备清单
42. Stock required spare parts
备品备件所需储存设施
43. Equipment manuals/specifications to Maintenance and Operating
Department
维修和操作部门的设备手册/说明
44. Vendor prints
供应商提供的印刷资料
45. Submit preventive maintenance requests (PM’s)
提交的预防性维修要求
46. Service contracts in place
服务合同已签订
47. Train maintenance personnel and document
培训维修人员和相关培训资料
Operational Items
生产项目
48. Develop SOP and special procedures – incorporate safety and
operational issues:
编写标准操作规程(SOP)及特殊操作规程——考虑了操作风险和可操
作性问题
49. Complete change control authorizations
完成变更控制授权
50. Develop/issue operating procedures:
制定/颁布下列操作规程
a) Initial start-up
初次开车
b) Normal start-up
正常开车
c) Normal operation
正常操作
d) Normal shutdown
正常停车
e) Emergency operations including emergency shutdown
包括急停急操作
Item No.
序号
Recommendation(Type Action Below or ‘not applicable’)
建议(请填写下列行动项或注明“不适用”)
结果
文件部分
f) Start-up following emergency shutdown
急停开车
g) Start-up following turnaround
大修后开车
h) Non-routine procedures (equipment clean-out, equipment
preparation for maintenance)
非常程序(设备清、设备维修准
i) Auxiliary equipment operation
设备的操作
51. Train operating personnel and document
培训操作人员和相关培训资料
52. Provide technical coverage
技术服务范围
53. What is the probability of containment failure? What are the
subsequent consequences? Review spill containment, rainwater
runoff, and fire water containment.
防泄漏设施的失效概率是多少?失效的后果是什?审查防泄漏设
施、量和消防水容量
Electrical Issues
电气问题
54. Panel access, clearance around panel, keys, etc.
配电的通、配电盘周围的间钥匙等
55. Cable entry section – glanding, housekeeping and other issues
缆接入部分—密封、保及其他问题
56. Panel power source identified? Multiple feeds?
配电的标?多供电?
57. Space heaters required?
需要加热
58. Lighting in panels
配电盘里
59. Canopies etc. for outdoor panels
用于室外配电雨棚等
60. Protection settings available?
有保设置
61. Panel board schedules
配电盘面板清单
62. Spare capacity available?
有备用容量
63. PPE available? HV mats, gloves
人防用品?有绝缘垫吗? 绝缘套吗?
64. Emergency/Standby power required?
有应/备用电源吗
65. VSD settings available – factory/commissioning
器设置—工/调试
66. Room access, permitting, maintainability, ingress/egress of
equipment
间通、许可证、可维修性、设备的进出
Item No.
序号
Recommendation(Type Action Below or ‘not applicable’)
建议(请填写下列行动项或注明“不适用”)
结果
文件部分
67. Pockets for drawings in panels?
配电的图纸集
68. Voltage warning labels?
电压警告标签
69. Ventilation sufficient?
通风充足吗
70. Suitability for area - IP rating, GMP suitability, hazardous area
classification.
区域适性——国际护等级GMP 性、险区域分类
-Relief Devices
-泄放设备
71. Are there standard markings on the P&ID?
P&ID 有标准代号
72. Do relief lines vent to a safe location?
线排放到一个安全
73. Are relief lines and relief devices secured and adequately sized?
线和泄放设备安全?尺寸足够大吗
74. Are there any isolation valves which will inhibit operation of relief
valves if closed? If YES, nominate Operations to monitor. If NO,
record no.
于关闭状态会抑制放阀操作的隔离?如果有,请定操作
人员监视。如果有,记录无
75. Is there a standard operating procedure for relief devices in place?
现场有泄放设备的标准操作规程
-For Field Verification
-现场
76. Is lighting sufficient?
充足吗
77. Is emergency lighting sufficient?
急照充足吗
78. Are steam pipes, valves, or traps situated within proximity of people
insulated?
于人接近范围蒸汽管线、阀门或水器被隔离
79. Is all instrumentation identified and tagged?
所有的仪表有标挂牌
80. Is there any rusted or damaged equipment?
任何或损的设备
81. Are swing gates installed on top of ladders or on access platforms?
在梯子顶部或平道上安装了回门
82. Review edge protection on platforms and heights. Will it protect
personnel and equipment? Is access adequate?
检查平高处边缘护。它能保人员和设备?通道足够吗
83. Do safety showers provide a hazard to people (slips), product
(contamination of systems), or ingress to electrical switchgear or
equipment?
安全喷淋对(滑跤)、产品(系统的污染)或部的电气开关
或设备产生险了
84. Are safety showers supplied from tempered water?
安全淋浴供应
Item No.
序号
Recommendation(Type Action Below or ‘not applicable’)
建议(请填写下列行动项或注明“不适用”)
结果
文件部分
85. Is chemical dosing within a safe proximity of people and product?
化学品操作是人和产品安全接近范围内吗
86. Label all pipe lines
所有的管线
87. Label all electric switches, disconnects, MCCs, control panels,
cables, etc.
标记所有的电气开关、中断器、电动机控制器、控制和电
88. Label vessels (material, hazard warnings)
List:
标记容器(材料、危警告)的清单
89. Seal wall penetrations
密封墙壁的渗透
90. Pour conduit seals
管的密封
91. Install fire extinguishers
92. Evacuation routes posted
93. Install appropriate area signs
94. Is all scaffolding and equipment removed; is general housekeeping
acceptable?
95. If there is potential for entrapment or exposure, has an E-Stop been
provided?
96. If full guarding is in place, has a lockable isolation device been
provided?
97. Pest control required in room/building?
98. MSDS sheets required?
99. Sprinklers in rooms?
100. Single point of failure condition? Has it been identified? – Record.
PSSR Checklist Example A-2
Pre-startup Safety Review Checklist
Inspection Date:
Department/Area:
Project Number:
Title/Equipment:
Signatures below indicate acceptance that the equipment or project is safe and satisfactory to
start-up with the exceptions noted.
Engineering / Maintenance Date
EHS Group Date
QA Group Date
Manufacturing / Operations Date
Project Engineer Date
Process Engineering Date
Checklist
Item No.
Details (reference category/item no.) Responsibility Complete
Sign &
Date
Category A Action Items - Items to be completed BEFORE authorization and start-up
1.
2.
3.
4.
5.
Category B Action Items - Items to be completed AFTER start-up
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
Sign below only when all punch list “before start-up” items are completed
Authorized: Facility/Equipment Owner Signature: Date
PSSR ITEM
NO.
CATEGORY/ITEM TO ASSESS Not
Applicable
1.1 GENERAL SAFETY
1.1.1 Have ALL appropriate personnel (Operations, Maintenance,
Technical, and Supervision) received adequate and
appropriate training on the equipment and operating
procedures?
1.1.2 Has adequate and appropriate PPE (Personal Protective
Equipment) been specified in the Work Procedures and/or
Standard Operating Procedures.
Has the PPE been provided?
Have the PPE users been trained in the use of the PPE?
Is the training documented?
1.1.3 Have measures been taken to adequately guard all dangerous
parts of this equipment?
1.1.4 Has sufficient provision been made for the electrical and/or
mechanical isolation of the equipment?
1.1.5 Are points of isolation clearly marked/labeled and readily
accessible?
1.1.6 Have bump/trip hazards been properly identified and
adequately marked?
Have all sharp edges been removed?
1.1.7 Has proper guarding, handrails/barriers, been provided to
prevent falls?
1.1.8 Have all hot/cold surfaces been adequately guarded to prevent
burns?
Are all cold surfaces adequately insulated to prevent
condensation drips (slip hazards)?
1.1.9 Are Safety Showers and Eye Wash facilities provided and
adequately marked?
Are the Safety Showers and Eye Wash facilities routinely
inspected?
Do the Safety Showers and Eye Wash facilities locations
comply with Corporate guidelines?
Are the Safety Showers and Eye Wash facilities readily visible
and accessible?
1.1.10 Has sufficient lighting been provided so that operation,
servicing, maintenance, and repair of the facilities can be
carried out safely?
1.1.11 Are notices, dials, screens, etc. for providing operational
instructions, safety warnings, and emergency information
provided, if required, and positioned so that they are clearly
visible and easily read?
1.1.12 Have all overhead fixtures, for example, pipe-hangers, pipe
sleeves, pipe sleeve covers, valve handles, floor opening
covers, etc., which could fall or be dislodged, been properly
secured?
1.1.13 Are all of the applicable Work Permit Procedures (Confined
Space Entry, Lock Out/Tag Out, Hot Work, High Work, etc.) in
place?
Have the Operating, Maintenance, and Supervisory personnel
been properly trained on the Work Permit Procedures?
PSSR ITEM
NO.
CATEGORY/ITEM TO ASSESS Not
Applicable
1.1.14 Has the fire protection systems been inspected by the
insurance company?
Has acceptance testing been completed and documented?
Is there an agreed on test and inspection program for the fire
protection systems (including alarm systems)?
1.2 MACHINERY/EQUIPMENT SAFETY
1.2.1 Has the machinery/equipment been installed so that it will be
stable and secure during operation?
1.2.2 Has all access to dangerous moving parts, or danger zones
created by the equipment, been prevented by the provision of
the correct guards, interlocks (both safety & non-safety) and/or
barriers?
1.2.3 Have the correct safety measures been taken to prevent any
risk from hot/cold surfaces, ejection of material, failure of parts
and their ejection, overheating/fire?
1.2.4 Has safe access been provided to the equipment that requires
operator and calibration and maintenance personnel access
for normal operations, adjustments, service, calibration,
maintenance, or repair?
Have slip, trip, trap, crush, entanglement, fall, bump, and cut
hazards been minimized?
1.2.5 Is the equipment provided with the properly identified
START/STOP and EMERGENCY controls that are positioned
for safe operation without hesitation, or loss of time, and
without ambiguity?
1.2.6 Is the equipment provided with a clearly identified means to
securely isolate it from ALL energy sources?
1.3 ERGONOMICS
1.3.1 Have the workstations, workplace, or equipment been
constructed so that need for stooping, bending stretching,
over-reaching and working over-head during operation has
been eliminated or minimized?
1.3.2 Has the need to lift, carry, push or pull heavy loads, or parts,
been eliminated to the extent possible?
1.3.3 Are all display screens, dials and START/STOP/
EMERGENCY buttons positioned so that they are readily
visible and accessible by the operating personnel?
1.3.4 Have Visual Display Screens been positioned so that
interference from glare is reduced to the minimum?
1.3.5 Have workstations been designed and equipped so that the
operator can adopt a comfortable position? (That is, able to
stand, or change position and sit upright, angle at elbows and
knees 90
, feet on floor.)
1.3.6 Does the operation of this equipment increase the risk of
Upper Limb Disorder; for example, repetitive tasks, handling
operations, machine paced work and prolonged operation?
1.4 OCCUPATIONAL HEALTH
1.4.1 Have all health risks arising from the gases, liquids, dusts,
mists, biological hazards or vapors used by, contained in or
emitted by this equipment been assessed?
Have the health risks been eliminated or are adequate
engineering controls utilized to minimize the risks?
1.4.2 Has adequate RPE (Respiratory Protective Equipment) been
specified in the Operating Procedures?
摘要:

开车检查表(质控部分)DescriptionofSystem/AreaUnderReview所审查系统/区域的描述Date日期Time时间ItemNo.序号Recommendation(TypeActionBelowor‘notapplicable’)建议(请填写下列行动项或注明“不适用”)结果文件部分1.2.3.4.5.6.7.8.SystemCheckoutItems系统检查项目9.Complete/documentqualityassuranceprogram:完成质量保证体系并建立了文档a)Receivedequipment=purchased收到的设备=购买的设备b)Adherenc...

展开>> 收起<<
34 化工厂常用PSSR检查表——国外.doc

共40页,预览40页

还剩页未读, 继续阅读

温馨提示:66文库网--作为在线文档分享平台,一直注重给大家带来优质的阅读体验;让知识分享变得简单、有价值;海量文档供您查阅下载,让您的工作简单、轻松而高效! 1. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。 2. 66文库网仅提供信息存储空间,仅对广大用户、作者上传内容的表现方式做保护处理,对上传分享的文档内容本身不做任何修改或编辑,并不对下载的任何内容负责。 3. 广大用户、作者上传的文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。 4. 本站不保证、不承担下载资源内容的准确性、安全性和完整性, 同时也不承担用户因使用下载资源对自己和他人造成任何形式的伤害或损失。
分类:管理文献 价格:1库币 属性:40 页 大小:870KB 格式:DOC 时间:2024-07-25
/ 40